Day 15 - 18. The dormer windows have been installed and fascia & soffit is fitted along the roof line. Treated tile battens are fixed and we're ready to start tiling the dormers. We finish the week with all external works completed including any additional works such as guttering and sealant where required, the scaffold can now be dismantled.
Loft conversion and Refurbishment, Bates Road Brighton