Day 2/3 - The first run of joists have been hung from the new steel beam, galvanised strapping is screwed to the existing ceiling joists and connected to the beam to replace the removed existing binders. Finally the eaves storage is insulated and boarded with 18mm moisture resistant chipboard. We're now ready to build the ashlar wall.
Loft conversion and Refurbishment, Bates Road Brighton
Updated: Dec 16, 2018